Get a solution

Moving two 180 tonne Fibre Optic Cables

Project info:

Load

2x Fibre Optic Cable

Weight

180t each

Location

Sweden

Destination

Pembrokeshire

Cable Transportation

We were instructed by Sumitomo Electrical Corporation (Sumitomo), a Japanese submarine cable manufacturer, to move two fibre optic cables , from the supplier in Sweden to the installation site in Pembrokeshire, Wales . Our role was to come up with a solution to get the fibre optic cable onboard the installation vessel.

A Happy Client

Sumitomo were able to deliver the cables on time for installation. The Fibre Optic cable was ready and waiting for them when they arrived in Wales. With our help, Sumitomo were able to focus on their own project, without the stress and distraction of moving the cable.

We took care of customs, and chartering the vessels, so all the logistics were taken care of. The baskets were such a success that the installation contractor has requested to rent the baskets for other projects.

Minimising costs

At Harlyn, we’re always looking for the most cost-effective solution for our clients. In this project, the way to minimise costs was to transport the cable with the minimum number of handlings.

Cables are typically “spooled” into carousels or baskets at fairly slow speeds of around 300 – 600m per hour, due to their weight and size.

If the cables were spooled directly onto the large construction vessel, the project would have incurred costs of £80K per day for the vessel charter. But with the help of our bespoke baskets, we were able to spool the cable onto a smaller vessel, the 2500 DWT coaster, which was significantly cheaper, at £4K per day.

The baskets we created were liftable (when empty and full), which meant that we could transfer the baskets from Sweden to Belgium.

The challenge:

Sumitomo required the cables for the Greenlink Interconnector project, a subsea and underground electricity interconnector that links the power markets in Ireland and Great Britain.

Bespoke baskets, designed and built for the project

The solution:

In order to transport the cables, we designed and built two baskets. We collaborated with our partners in Rotterdam for the building phase.

Designing Baskets

In designing the baskets, we used finite element analysis and 3D design to create baskets that complied with DNV Design Rules, and were suitable to carry 180 tonnes of cable. Each basket weighed 200 tonnes and measured 9m in diameter.

We transported the baskets from Rotterdam to Sweden by road. We designed them specifically to be road transportable without a permit to reduce time and cost.

In Sweden, we spooled the fibre optic cable into the basket. Then we lifted the basket onto a 2500 DWT Coaster using a shore crane.

Next we sailed the cable from Sweden to Belgium. In Belgium, we lifted each basket from the vessel to the quayside, using a sheer leg crane.

Outcome

One of the cables went into long term storage. The other cable was taken offshore immediately to be laid. Once laid, we received back the basket, and 1,600m of cable , which we spooled to the reel on the quayside. We broke down the baskets and transported the baskets and the fibre optic cable to the UK.

Kris Tait

Working with Sumitomo Electrical Corporation on relocating fiber optic cables from Sweden to Wales was a rewarding challenge. Our team expertly managed logistics and coordination to ensure the safe and precise transfer of cables onto the installation vessel. This project showcased our dedication to excellence and innovation in complex marine operations.

Head of Projects, Harlyn Solutions

Engineering-led transportation
in action.

Transporting OSPs for a flagship windfarm in Moray West

Distance Weight Location Destination 300 miles 1400 tons Newcastle Moray West

View case study
Harlyn Solutions

Organise, Engineer, Save

Understanding all aspects of the challenge.

View case study

Lifting a 170 tonne linkspan to its new facility in Liverpool

Harlyn Solutions worked with MacGregor to lift and install a linkspan at the new Isle of Man Ferry Terminal in Liverpool — completing a complex, multi-phase project spanning 30 months. From transport from Poland to final installation, our team provided flexible, responsive support and acted as a single point of contact to manage evolving challenges efficiently.

View case study

Spooling Flexible Flowlines

Harlyn Solutions developed a world-first engineering solution to supply two 14 km flexible flowlines for a subsea development project, tying back seven wells and subsea trees. Our team safely spooled the flowlines onto barge baskets, enabling the client to continue production of the next 4,500 tonnes of piping efficiently.

View case study

Give us a call.
We’ll give you a solution.
Go back to changing the world.